LESCO Peak & Off-Peak Hours
PEAK
/ OFF PEAK TIMINGS
|
||
Season
|
Peak Timing
|
Off-Peak Timing
|
Dec to
Feb
|
5 PM
to 9 PM
|
Remaining
20 hours
|
Mar to
May
|
6 PM
to 10 PM
|
-do-
|
Jun to
Aug
|
7 PM
to 11 PM
|
-do-
|
Sep to
Nov
|
6 PM
to 10 PM
|
-do-
|
LESCO Electricity Unit Price
Lesco electricity unit price for domestic users are as follow:
1st 100 units price = Rs – 12.90 / unit
After 100 units price = Rs – 13.54 / unit
SCHEDULE OF ELECTRICITY TARIFF W.E.F 2019
A1 General Supply Tariff-Residential
|
|||||||||||
Sr. No.
|
Tariff Category/Particulars
|
Fixed Charges Rs/KW/M
|
Uniform Tariff Variable Charges (Rs/KWh)
|
Nepra Variable Charges Rs/kwh |
Applicable Variable Charges |
||||||
Government Subsidy
|
|||||||||||
Fixed Charges Rs/Kw/M
|
Variable Charges Rs/Kw/M
|
||||||||||
a) | For Sanctioned load less than 5 kW | ||||||||||
i | Up to 50 Units | – | 4.00 | 4.0 | 2.0 | 2.0 | |||||
For Consumption exceeding 50 Units | – | – | |||||||||
ii | For first 100 Units | – | 13.85 | 12.09 | 5.79 | 6.3 | |||||
iii | a.101-200 Units | 15.86 | 13.54 | 8.11 | 5.43 | ||||||
iii | b.201-300 Units | – | 16.83 | 15.27 | 10.20 | 5.07 | |||||
iv | 301-700 Units | – | 18.54 | 16.91 | 17.60 | -0.69 | |||||
v | Above 700 Units | – | 20.94 | 19.24 | 20.70 | -1.46 | |||||
b) | For Sanctioned load 5 kW & above | ||||||||||
Peak | Off-Peak | Peak | Off-Peak | Peak | Off-Peak | Peak | Off-Peak | ||||
Time of Use | – | 19.33 | 12.80 | 18.81 | 12.5 | 20.70 | 14.38 | – | -1.89 | -1.88 | |
As per Authority’s decision residential consomer will be given the benefits of only one previous slab | |||||||||||
Under Tariff A-1, there
shall be minimum monthly customer charge at the following rates even
if no energy is consumed. a) Single Phase connections: Rs. 75/- per consumer per month b) Three phase connection: Rs.150/- per consumer per month |
|||||||||||
A2 General Supply Tariff-Commercial
|
|||||||||||
Sr. No.
|
Tariff Category/Particulars
|
Fixed Charges Rs/KW/M
|
Uniform Tariff Variable Charges (Rs/KWh)
|
Nepra Variable Charges Rs/kwh | Applicable Variable Charges | ||||||
Government Subsidy
|
|||||||||||
Fixed Charges Rs/Kw/M
|
Variable Charges Rs/Kw/M
|
||||||||||
a) | For Sanctioned load less than 5 kW | 19.26 | 19.08 | – | 18 | – | 1.08 | ||||
b) | For Sanctioned load 5 kW & above | 400.00 | 18.01 | 16.81 | – | 19.68 | – | -2.87 | |||
Peak | Off-Peak | Peak | Off-Peak | Peak | Off-Peak | Peak | Off-Peak | ||||
c) | Time of Use | 400.00 | 20.09 | 13.48 | 19.18 | 12.26 | 21.6 | 15.63 | – | -2.42 | -3.37 |
Under Tariff A-2, there
shall be minimum monthly customer charge at the following rates
even if no energy is consumed. a) single phase connections: Rs. 175/- per consumer per month b) Three phase connections: Rs. 350/- per consumer per month |
|||||||||||
A3 General Services
|
|||||||||||
Sr. No.
|
Tariff Category/Particulars
|
Fixed Charges Rs/KW/M
|
Uniform Tariff Variable Charges (Rs/KWh)
|
Nepra Variable Charges Rs/kwh |
Applicable Variable Charges |
||||||
Government Subsidy
|
|||||||||||
Fixed Charges Rs/Kw/M
|
Variable Charges Rs/Kw/M
|
||||||||||
a) | General Services | 17.56 | 17.6 | – | 17.56 | – | 0.04 | ||||
Under Tariff A-3, there
shall be minimum monthly customer charge at the following rates
even if no energy is consumed. a) single phase connections: Rs. 175/- per consumer per month b) Three phase connections: Rs. 350/- per consumer per month |
|||||||||||
|
|||||||||||
B Industrial Supply Tariff
|
|||||||||||
Sr. No.
|
Tariff Category/Particulars
|
Fixed Charges Rs/KW/M
|
Uniform Tariff Variable Charges (Rs/KWh)
|
Nepra Variable Charges Rs/kwh |
Applicable Variable Charges |
||||||
Government Subsidy
|
|||||||||||
Fixed Charges Rs/Kw/M
|
Variable Charges Rs/Kw/M
|
||||||||||
B1 (a | Up to 25 kw (at 400/230 volts) | – | 18.32 | 17.59 | – | 15.28 | – | 2.31 | |||
B2(a) | exceeding 25-500 Kw (at 400 Volts) | 400.00 | 15.79 | 14.95 | – | 14.78 | – | 0.17 | |||
Time of Use | Peak | Off-Peak | Peak | Off-Peak | Peak | Off-Peak | Peak | Off-Peak | |||
B1 (b) | Up to 25 kw | – | 20.14 | 13.46 | 19.88 | 12.03 | 18.84 | 13.28 | – | 1.04 | -1.25 |
B2 (b) | exceeding 25-500 Kw (at 400 Volts) | 400.00 | 19.93 | 13.23 | 19.35 | 12.64 | 18.78 | 13.07 | – | 0.57 | -0.53 |
B3 | |||||||||||
For All Loads up to 5000 KW(at 11,33 KV) | 380.00 | 20.39 | 12.61 | 20.58 | 11.61 | 18.78 | 12.98 | – | 1.8 | -1.37 | |
B4 | For All Loads (at 66,132 KV & above) | 360.00 | 20.27 | 13.25 | 20.25 | 12 | 18.78 | 12.88 | – | 1.47 | -0.88 |
For B1 consumers there shall be fixed
minimum charge of Rs. 350 per month. For B2 consumers there shall be fixed minimum charge of Rs. 2,000 per month. For B3 consumers there shall be fixed minimum charge of Rs. 50,000 per month. For B4 consumers there shall be fixed minimum charge of Rs. 500,000 per month. |
|||||||||||
|
|||||||||||
C-SINGLE POINT SUPPLY FOR PURCHASE IN BULK BY A DISTRIBUTION LICENSEE AND MIXED LOAD CONSUMERS NOT FALLEN IN ANY OTHER CONSUMER CLASS
|
|||||||||||
Sr. No.
|
Tariff Category/Particulars
|
Fixed Charges Rs/KW/M
|
Uniform Tariff Variable Charges (Rs/KWh)
|
Nepra Variable Charges Rs/kwh |
Applicable Variable Charges |
||||||
Government Subsidy
|
|||||||||||
Fixed Charges Rs/Kw/M
|
Variable Charges Rs/Kw/M
|
||||||||||
C-1 | For supply at 400/230 Volts | ||||||||||
a) | Sanctioned load less than 5 kW | – | 21.32 | 16.2 | 18.68 | – | -2.48 | ||||
b) | Sanctioned load 5 kW & up to 500 kW | 400 | 20.13 | 15.7 | 18.18 | – | -2.48 | ||||
C-2(a) | For supply at 11,33 kV up to and including 5000 kW | 380 | 15.61 | 15.21 | 17.98 | – | -2.77 | ||||
C-3(a) | For supply at 66 kV & above and sanctioned load above 5000 kW | 360 | 14.42 | 13.97 | 17.88 | – | -3.91 | ||||
Time Of Use | Peak | Off Peak | Peak | Off Peak | Peak | Off Peak | Peak | Off-Peak | |||
C-1© | For supply at 400/230 Volts 5 kW & up to 500 kW | 400 | 21.52 | 14.99 | 19 | 12.5 | 21.6 | 15 | – | -2.6 | -2.5 |
C-2(b) | For supply at 11,33 kV up to and including 5000 kW | 380 | 19.73 | 12.57 | 19 | 12.1 | 21.6 | 14.8 | – | -2.6 | -2.7 |
C-3(b) | For supply at 66 kV & above and sanctioned load above 5000 kW | 360 | 18.49 | 11.59 | 19 | 12 | 21.6 | 14.7 | – | -2.6 | -2.7 |
D-AGRICULTURE TARIFF
|
|||||||||||
Sr. No.
|
Tariff Category/Particulars
|
Fixed Charges Rs/KW/M
|
Uniform Tariff Variable Charges (Rs/KWh)
|
Nepra Variable Charges Rs/kwh |
Applicable Variable Charges |
||||||
Government Subsidy
|
|||||||||||
Fixed Charges Rs/Kw/M
|
Variable Charges Rs/Kw/M
|
||||||||||
D-1(a) | SCARP less than 5 KW | – | 23.17 | 23.17 | 15.68 | – | 7.49 | ||||
D-2 | Agricultural Tube Well | 200 | 14.56 | 14.56 | – | 5.35 | – | 9.21 | |||
Peak | Off Peak | Peak | Off Peak | Peak | Off-Peak | Peak | Off-Peak | ||||
D-1(b) | SCARP 5 KW & above | 200 | 20.87 | 14.03 | 22 | 12.02 | 18.6 | 11.35 | – | 3.4 | 0.67 |
D-1(b) | Agricultural 5 KW & above | 200 | 20.27 | 13.04 | 20.5 | 13.46 | 5.35 | 5.35 | – | 15.15 | 8.11 |
Under this tariff, there shall be minimum monthly charges Rs. 2000/- per consumer per month, even if no energy is consumed.
Note: The consumers having sanctioned load less than 5 kW can opt for TOU metering.
|
|||||||||||
|
|||||||||||
E-TEMPORARY SUPPLY TARIFF
|
|||||||||||
Sr. No.
|
Tariff Category/Particulars
|
Fixed Charges Rs/KW/M
|
Uniform Tariff Variable Charges (Rs/KWh)
|
Nepra Variable Charges Rs/kwh |
Applicable Variable Charges |
||||||
Government Subsidy
|
|||||||||||
Fixed Charges Rs/Kw/M
|
Variable Charges Rs/Kw/M
|
||||||||||
E-1(i) | Residential Supply | – | 20.84 | 18.15 | 20.84 | – | -2.69 | ||||
E-1(ii) | Commercial Supply | – | 18.39 | 18.47 | 18.39 | – | 0.08 | ||||
E-2 | Industrial Supply | – | 16.36 | 14.70 | 16.36 | – | -1.66 | ||||
Note : For the categories of E-1(i&ii)
above, the minimum bill of the consumers shall be Rs. 50/- per day
subject to a minimum of Rs. 500/- for the entire period of supply,
even if no energy is consumed.
|
|||||||||||
|
|||||||||||
F – Seasonal Industrial Supply TARIFF
|
|||||||||||
125% of relevant
Industrial Tariff
|
|||||||||||
Note: Tariff F
consumers will have the option to convert to regular tariff and
vice versa. This option can be exercised at the time of a new connection
or at the beginning of the season. Once exercised, the option remains
in force for at least one year.
|
|||||||||||
|
|||||||||||
G-PUBLIC LIGHTING
|
|||||||||||
Sr. No.
|
Tariff Category/Particulars
|
Fixed Charges Rs/KW/M
|
Uniform Tariff Variable Charges (Rs/KWh)
|
Nepra Variable Charges Rs/kwh |
Applicable Variable Charges |
||||||
Government Subsidy
|
|||||||||||
Fixed Charges Rs/Kw/M
|
Variable Charges Rs/Kw/M
|
||||||||||
Street Lighting | – | 18.78 | 19.78 | 18.68 | 1.1 | ||||||
Under Tariff-G, there shall be a minimum monthly
charge of Rs. 500/- per month per kW of lamp capacity installed.
|
|||||||||||
|
|||||||||||
H- RESIDENTIAL COLONIES ATTACHED TO INDUSTRIAL PREMISES
|
|||||||||||
Sr. No.
|
Tariff Category/Particulars
|
Fixed Charges Rs/KW/M
|
Uniform Tariff Variable Charges (Rs/KWh)
|
Nepra Variable Charges Rs/kwh |
Applicable Variable Charges |
||||||
Government Subsidy
|
|||||||||||
Fixed Charges Rs/Kw/M
|
Variable Charges Rs/Kw/M
|
||||||||||
Residential Colonies attached to industrial premises | – | 18.42 | 20.39 | – | 18.68 | 1.71 | |||||
I – RAILWAY TRACTION
|
|||||||||||
Sr. No.
|
Tariff Category/Particulars
|
Fixed Charges Rs/KW/M
|
Uniform Tariff Variable Charges (Rs/KWh)
|
Nepra Variable Charges Rs/kwh |
Applicable Variable Charges |
||||||
Government Subsidy
|
|||||||||||
Fixed Charges Rs/Kw/M
|
Variable Charges Rs/Kw/M
|
||||||||||
Railway Traction | – | 17.9 | 17.9 | 18.68 | -0.78 | ||||||
J- SPECIAL CONTRACTS UNDER NEPRA (SUPPLY OF POWER)
|
|||||||||||
Sr. No.
|
Tariff Category/Particulars
|
Fixed Charges Rs/KW/M
|
Uniform Tariff Variable Charges (Rs/KWh)
|
Nepra Variable Charges Rs/kwh |
Applicable Variable Charges |
||||||
Government Subsidy
|
|||||||||||
Fixed Charges Rs/Kw/M
|
Variable Charges Rs/Kw/M
|
||||||||||
J-1 | For supply of 66 kv & above and having sactioned load of 20MW & above | 360.00 | 16.14 | 11.77 | 17.88 | -6.11 | |||||
J-2(a) | For supply at 11,33 kv | 380.00 | 16.46 | 14.1 | 17.98 | -3.88 | |||||
J-2(b) | For supply at 66 kv & above | 360.00 | 16.36 | 14 | – | 17.88 | -3.88 | ||||
J-3(a) | For supply at 11,33 kv | 380.00 | 16.46 | 14.1 | – | 17.98 | -3.88 | ||||
J-3(b) | For supply at 66 kv & above | 360.00 | 16.36 | 14 | – | 17.88 | -3.88 | ||||
Time of Use | Peak | Off-Peak | Peak | Off-Peak | Peak | Off-Peak | Peak | Off-Peak | |||
J-1 (b) | For supply of 66 kv & above and having sactioned load of 20MW & above | 360 | 20.66 | 14.33 | 18.60 | 11.62 | 21.60 | 14.70 | – | -3.0 | -3.08 |
J-2 (c) | For supply at 11,33 kv | 380.00 | 20.66 | 14.44 | 18.60 | 11.72 | 21.60 | 14.80 | – | -3.0 | -3.08 |
J-2(d) | For supply at 66 kv & above | 360.00 | 20.66 | 14.33 | 18.60 | 11.62 | 21.60 | 14.70 | – | -3.0 | -3.08 |
J-3(c) | For supply at 11,33 kv | 380.00 | 20.66 | 14.44 | 18.60 | 11.72 | 21.60 | 14.80 | – | -3.0 | -3.08 |
J-3(d) | For supply at 66 kv & above | 360.00 | 20.66 | 14.33 | 18.60 | 11.62 | 21.60 | 14.70 | – | -3.0 | -3.08 |
Note: | |||||||||||
1:- Neelum Jhelum Surcharge at rate of Rs. 0.10 per KWh on all electricity consumers except lifeline domestic consumers of the category ‘Residential-A’ for Electricity Sold. | |||||||||||
2:- Financial Cost Surcharge at the rate of Rs. 0.43 per KWh applicable to all the categories of Electricity Consumers except lifeline domestic consumers of the Category ‘Residential-A’ for Electricity sold. |
Frequently Asked Question
What is Per Unit Rate of Electricity in Lahore?
Electricity unit price is different for each plan, here I’m sharing the electricity unit price of domestic connection. Electricity unit price of domestic connections is Rs-12.09 per unit for 1st 100 units and after 1st 100 units it will increase into Rs-13.54 per unit.
What are LESCO Peak Hours?
LESCO peak hours are as follow:
- Dec to Feb – 5 to 9 PM
- Mar to May – 6 to 10 PM
- Jun to Aug – 7 to 11 PM
- Sep to Nov – 6 to 10 PM
Rest are off-peak hours that are 20 hours.
What is LESCO Tariff?
LESCO tariff is the type of connection that LESCO is offering to their consumers as per their requirements e.g Domestic, Commercial, General Services, Industrial, Agriculture, Temporary Supply, Public Lighting, and Residential Colonies etc.